Immission control - Apply for partial authorisation for the construction and operation of a plant in accordance with BImSchG
The construction, operation and significant modification of an installation listed in Annex 1 of the Fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Installations Subject to Authorisation - 4th BImSchV) require an immission control permit from the competent authority. All environmental impacts of the plant must be considered and assessed in the authorisation procedure.
Upon application, it is also possible to issue such a permit in stages or in stages by means of several partial permits. With a partial licence, you can already begin with the construction and operation of the approved project section. In individual cases, a partial permit can therefore help to speed up the realisation of a project.
Forms/Online Services
Responsible authority
Contact
Contact
Details
Prerequisite
A partial licence may only be granted if the licensing requirements for the part of the installation comprising the partial licence are met and there is a legitimate interest in granting a partial licence. In addition, it must be possible to confirm the overall approvability of the entire project in a preliminary forecast. Individual issues must not be excluded from this process.
Procedure
The application for a partial permit is made as part of an authorisation procedure under immission control law, which requires requires a written or electronic application. To apply for an immission control permit electronically, you can use the online application "Applying for a permit under the Federal Immission Control Act", which adapts to the information you provide, guides you through the application process and provides specific technical information.
The application must be accompanied by the drawings, explanations and other documents required to check the authorisation requirements. If further documents are required by the responsible immission control authority or the relevant specialised authorities for an assessment, these must be submitted subsequently.
The procedure for a partial permit corresponds to that of a formal or simplified permit procedure for the construction and operation of an installation requiring a permit under immission control legislation. The parts of the entire installation not covered by the partial licence must be approved by further partial licences.
Deadlines
You must obtain authorisation from the competent authority before constructing and starting to operate an installation that requires authorisation.
Required documents
The application must be accompanied by the documents required for an assessment. These are, for example
- Descriptions of the project, including information on plant components, process steps, material and product data,
- schematic diagrams and flow charts,
- Information on possible disruptions to normal operation,
- Information on emissions and immissions,
- Information on waste and waste water,
- Construction documents: site plan, construction drawings, construction description.
The competent authority may request further documents if necessary. Coordinate in advance with the responsible immission control authority or the specialised authorities involved in the procedure regarding the documents required for an assessment.
If official decisions concerning the installation are communicated as part of the authorisation procedure (e.g. building permit), the documents required for this must also be submitted.
The application must always be made using the forms for the application for authorisation under immission control law. The forms and further information on the immission control authorisation procedure can be found in the Guideline - Authorisation and notification procedure in accordance with the Federal Immission Control Act of the Baden-Württemberg Ministry of the Environment.
Costs
The fees are based on the investment costs for the system.
Processing time
As a rule, the licensing authority must check whether the documents are complete within one month of receiving the application. If the application documents are not sufficient for an assessment, they must be completed by the applicant.
Once the application documents are complete, the statutory deadlines begin for the authorisation procedure under immission control law, which is seven months for new installations in a formal procedure and three months in a simplified procedure. For modification projects, the statutory period is six months in a formal procedure and three months in a simplified procedure. The deadlines can be extended by three months if this is necessary due to the difficulty of the examination or for reasons attributable to the applicant.
Miscellaneous
Coordinate in advance with the responsible immission control authority regarding the required documents.
The electronic application for a partial permit for an installation requiring a permit is made using the same online application that is used to apply for the construction and operation of a new installation. The procedure option is selected during the application process.
Legal basis
Bundesimmissionsschutzgesetz (BImSchG):
- § 4 Genehmigung
- § 5 Pflichten der Betreiber genehmigungsbedürftiger Anlagen
- § 8 Teilgenehmigung
- § 10 Genehmigungsverfahren
Vierte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über genehmigungsbedürftige Anlagen - 4. BImSchV)
Neunte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über das Genehmigungsverfahren - 9. BImSchV)