Immission control - applying for the construction and operation of a plant requiring authorisation in accordance with the BImSchG
The construction and operation of an installation listed in Annex 1 of the Fourth Ordinance on the Implementation of the Federal Immission Control Act (4th BImSchV) requires an immission control licence from the competent authority. All environmental impacts of the plant must be considered and assessed in the authorisation procedure.
Forms/Online Services
Responsible authority
Contact
Contact
Details
Prerequisite
The permit must be granted if it is ensured that the obligations arising from the Federal Immission Control Act (BImSchG) and its legal ordinances are fulfilled and that other public law regulations and occupational health and safety concerns do not conflict with the construction and operation of the plant. Authorisation can only be granted if the application documents submitted by you allow a complete and final assessment of the project's eligibility for authorisation.
Procedure
- The authorisation procedure requires a written or electronic application. To apply electronically for an immission control permit, you can use the online application "Applying for a permit under the Federal Immission Control Act", which adapts to the information you provide, guides you through the application process and provides specific technical information.
- The application must be accompanied by the drawings, explanations and other documents required to check the authorisation requirements. If further documents are required by the responsible immission control authority or the relevant specialised authorities for an assessment, these must be submitted subsequently.
- If the application is complete, it must be publicised in the case of formal procedures and then displayed for one month. In simplified authorisation procedures or if public participation is waived, there is no public display of the application documents. At the latest at the same time as the public announcement of the project, the approval authority requests the authorities to be involved to submit their comments on the approval requirements. If there are any objections, these will be discussed with you and those who raised the objections in a public meeting or an online consultation.
- Once the licensing authority has determined all the circumstances that are relevant to the granting of a licence, a decision must be made on the application. The authorisation decision must be substantiated in writing and will be sent to you and the persons who have raised objections. The notification of the authorisation notice to objectors can be replaced by a public announcement.
- Pursuant to Section 13 BImSchG, the immission control permit includes other official decisions relating to the plant, in particular permits, approvals, concessions, authorisations and licences under public law. Excluded from this are planning approvals, approval of operating plans under mining law, official decisions based on nuclear regulations and water law permits and authorisations.
- As part of the application, an application can also be made for approval of an early start in accordance with Section 8a BImSchG or the granting of a preliminary decision in accordance with Section 9 BImSchG as well as the division into several partial authorisations in accordance with Section 8 BImSchG.
Deadlines
You must obtain authorisation from the competent authority before erecting and starting to operate an installation that requires authorisation.
Required documents
The application must be accompanied by the documents required for an assessment. These are, for example
- Descriptions of the project, including information on plant components, process steps, material and product data,
- schematic diagrams and flow charts,
- Information on possible disruptions to normal operation,
- Information on emissions and immissions,
- Information on waste and waste water,
- Construction documents: site plan, construction drawings, construction description.
The competent authority may request further documents if necessary. Coordinate in advance with the responsible immission control authority regarding the documents required for an assessment.
If official decisions concerning the installation are communicated as part of the authorisation procedure (e.g. building permit), the documents required for this must also be submitted.
The application must always be made using the forms for the application for authorisation under immission control law. The forms and further information on the immission control authorisation procedure can be found in the Guideline - Authorisation and notification procedure in accordance with the Federal Immission Control Act of the Baden-Württemberg Ministry of the Environment.
Costs
The fees are based on the investment costs for the system.
Processing time
As a rule, the licensing authority must check whether the documents are complete within one month of receiving the application. If the application documents are not sufficient for an assessment, they must be completed by the applicant.
Once the application documents are complete, the statutory deadlines begin for the authorisation procedure under immission control law, which is seven months for new installations in a formal procedure and three months in a simplified procedure. The deadlines can be extended by three months if this is necessary due to the difficulty of the examination or for reasons attributable to the applicant.
Miscellaneous
Coordinate in advance with the responsible immission control authority regarding the documents required for an assessment.
The application for an immission control permit in the simplified or formal authorisation procedure is made using the same online application. The procedure variant is selected during the application process.
Significant changes to an installation requiring authorisation under immission control law also require authorisation and can be applied for using the same online application.
When submitting an electronic application via the Baden-Württemberg service portal, please use the online process "Submitting documents for immission control authorisation" for the subsequent submission of application documents.
Legal basis
Bundesimmissionsschutzgesetz (BImSchG):
- § 4 Genehmigung
- § 5 Pflichten der Betreiber genehmigungsbedürftiger Anlagen
- § 6 Genehmiungsvoraussetzungen
- § 10 Genehmigungsverfahren
Vierte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über genehmigungsbedürftige Anlagen - 4. BImSchV)
Neunte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über das Genehmigungsverfahren - 9. BImSchV)