Barrierefreiheit optimieren - passen Sie die Darstellung Ihren Bedürfnissen an.
Immission control - Notification if the action values are exceeded or if the operation of evaporation, cooling systems and wet cutters is disrupted
As the operator of an evaporative cooling system, a cooling tower or a wet separator, you are obliged to inform the competent authority immediately in accordance with Annex 3 Part 1 of the 42nd BImSchV and within a period of 4 weeks in accordance with Annex 3 Part 2 of the 42nd BImSchV if a laboratory test reveals that the action values for the concentration of legionella in process water specified in Annex 1 of the 42nd BImSchV have been exceeded. The competent authority will receive the information and check the measures you have initiated. If necessary, the authority will also contact you.
Forms/Online Services
- KaVKA-42.BV Web-Anwendung KaVKA-42.BV dient der Anzeige von Verdunstungskühlanlagen, Kühltürmen und Nassabscheidern gemäß § 13 der 42. Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über Verdunstungskühlanlagen, Nassabscheider und Kühltürme - 42. BImSchV)
Responsible authority
Contact
Contact
Contact
Details
Prerequisite
As the operator of an evaporative cooling system, a cooling tower or a wet separator, you are obliged to inform the competent authority if a laboratory test reveals that the action values for the concentration of legionella in process water have been exceeded.
Procedure
The nationwide standardised web application KaVKA-42.BV is available for operators of to fulfil their information obligations.
The use of the KaVKA-42.BV web application is mandatory in Baden-Württemberg for all notification obligations under § 13 and for all information obligations under § 10 of the 42nd BImSchV. In addition, the web application can be used for notifications under § 14.
Deadlines
If a measure value is exceeded, you are obliged, among other things, to inform the competent authority immediately in accordance with Annex 3 Part 1 and within a period of 4 weeks in accordance with Annex 3 Part 2.
Required documents
Information in accordance with Annex 3 Part 1 or 2 of the 42nd BImSchV and in particular
- Result of the laboratory test in which the exceedance of the action value according to Annex 1 was determined (§ 10 sentence 1 number 1 of the 42nd BImSchV),
- Result of the test for the differentiation of legionella according to § 9 paragraph 1 number 1 (§ 10 sentence 1 number 2 of the 42nd BImschV),
- Result of the additional laboratory test according to § 9 paragraph 1 number 3 (§ 10 sentence 1 number 2 of the 42nd BImschV).
When using the web application KaVKA-42.BV, all required information is requested.
Costs
The costs are based on the fees set by the responsible immission control authorities.
Miscellaneous
If you have any technical questions about the KaVKA-42.BV web application (e.g. questions about using the software, registration problems), please contact the Baden-Württemberg Environmental Agency (LUBW):
- kavka@lubw.bwl.de
For technical questions (e.g. questions on the classification of an installation and the scope of application of the 42nd BImSchV, questions on installations already registered in KaVKA-42.BV, questions on individual operator obligations), please contact your responsible immission control authority.
Legal basis
Bundesimmissionsschutzgesetz (BImSchG)
Zweiundvierzigste Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über Verdunstungskühlanlagen, Kühltürme und Nassabscheider - 42. BImSchV)
- § 10 Informationspflichten
Vierte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes (Verordnung über genehmigungsbedürftige Anlagen - 4. BImSchV)
Wasserhaushaltsgesetzt (WHG)
Richtlinie 2010/75/EU des Europäischen Parlaments und des Rates vom 24. November 2010 über Industrieemissionen
Immissionsschutz-Zuständigkeitsverordnung des Landes Baden-Württemberg
Allgemeinverfügung des Ministeriums für Umwelt, Klima und Energiewirtschaft zur Nutzung des elektronischen Weges bei der Erfüllung von Anzeige- und Informationspflichten nach der Verordnung über Verdunstungskühlanlagen, Kühltürme und Nassabscheider - 42. BImSchV
Release note
Machine generated, based on the German release by: Umweltministerium Baden-Württemberg, 05.08.2024