Submit an air pollution control measurement report on continuous measurements of air pollutants at facilities for the biological treatment of waste in accordance with the 30th BImSchV
If you are the operator of a biological waste treatment plant, you must continuously determine, record and analyse the air pollutant emissions for certain air pollutants by means of continuous measurements with special measuring devices.
You must prepare a measurement report analysing the measurements and send it to the immission control authority responsible for you within certain deadlines.
Forms/Online Services
Responsible authority
Contact
Contact
Details
Prerequisite
You are the operator of a plant for the biological treatment of waste in accordance with the 30th BImSchV.
Procedure
- You analyse the continuous measurements of each calendar year
- You prepare a measurement report on the results.
- You send the measurement report to the immission control authority responsible for you by the deadline.
Deadlines
- You must submit the measurement report to the responsible immission control authority within 3 months of the end of each calendar year.
- You must keep the records of the measuring devices for at least 5 years after preparing the measurement report.
Required documents
Complete measurement report
Costs
None
Miscellaneous
Please ensure that you submit the measurement report to the immission control authority responsible for your plant.
Legal basis
Bundes-Immissionsschutzgesetz (BImSchG)
- § 26 Messungen aus besonderem Anlass
- § 29 Kontinuierliche Messungen
Verordnung über Anlagen zur biologischen Behandlung von Abfällen – 30. BImSchV
- § 9 Kontinuierliche Messungen
- § 10 Auswertung und Beurteilung von kontinuierlichen Messungen
Release note
machine generated, based on the German release by: Umweltministerium Baden-Württemberg, 10.07.2026